Route 219 Expressway Phase 1 (SR-99 to Morrow Road)

Description: Near Salida on Route 219 from Route 99 to Morrow Rd. Widen to a 4-lane expressway. Phase 1 from PM 0.1-2.9.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Stanislaus
City Modesto, Salida
Zip Code 95356, 95368
 
Senate District
14
Assembly District 25
Congressional District 19
 
Caltrans District
10
 
 
County/State Route Stanislaus 219
Postmile Begin/End 0.1 2.9
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)  940    940  
Lane Miles Added (HOV)      0  
Lane Miles Added (Mixed)  6.7    6.7  
Peak Period Time Savings (minutes)  37418    37418  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Caltrans Zelie Nogueira (209) 948-3930   zelie.nogueira@dot.ca.gov
Design (PS&E) Phase
Caltrans Zelie Nogueira (209) 948-3930   zelie.nogueira@dot.ca.gov
Right of Way Phase
Caltrans Zelie Nogueira (209) 948-3930   zelie.nogueira@dot.ca.gov
Construction Phase
Caltrans Zelie Nogueira (209) 948-3930   zelie.nogueira@dot.ca.gov
 
Corridor System Management Plan
Caltrans Zelie Nogueira (209) 948-3930   zelie.nogueira@dot.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
CMIA
$14,760 $-6,143 $8,617
Non-bond Funding
State/Federal*
$35,020 $716 $35,736
Non Budgeted ETC
$0 $0 $0
 
Total**** $49,780 $-5,427 $44,353

**** Totals may not add up exactly to column amounts due to rounding

# Approved is planned budget

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$1,520 $128 $1,648 $1,621
Design(PS&E)
$2,000 $828 $2,828 $2,891
Right of Way
$31,260 $0 $31,260 $19,743
Construction
$15,000 $-6,383 $8,617 $8,564
 
Total* $49,780 $-5,427 $44,353 $32,820

* Totals may not add up exactly to column amounts due to rounding

** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
10/01/1998 

05/01/2004 
 

 
10/01/1998 

05/01/2004 
100  10/01/1998 

05/13/2004 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
10/01/2004 

06/01/2007 
 

 
10/01/2004 

06/01/2007 
100  05/13/2004 

06/28/2007 


-1 
Begin Right of Way Phase

End Right of Way Phase
01/01/2005 

06/01/2007 
 

 
01/01/2005 

06/01/2007 
100  10/01/2004 

03/10/2008 


-9 
Begin Construction Phase

End Construction Phase
11/01/2007 

08/01/2009 
 

 
11/01/2007 

08/01/2009 
100  07/09/2008 

06/30/2010 
-8 

-11 
Begin Closeout Phase

End Closeout Phase
10/01/2009 

11/01/2009 
 

 
10/01/2009 

11/01/2009 
06/30/2010 

07/28/2016 
-9 

-82 
Corridor System Management Plan
Adoption Date 10/01/2008    10/01/2008  09/28/2008 
Implementation Date 02/01/2009    02/01/2009   
????????
Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 940 940
Lane Miles Added (HOV) 0
Lane Miles Added (Mixed) 6.7 6.7
Peak Period Time Savings (minutes) 37418 37418

Bond Funding Cost
Adopted:
$14,760,000
Current Approved:
$9,844,000
Actual Expenditures:
$8,564,000

 

Status as of December 31, 2023.