Route 219 Expressway Phase 1 (SR-99 to Morrow Road) |
Description: Near Salida on Route 219 from Route 99 to Morrow Rd. Widen to a 4-lane expressway. Phase 1 from PM 0.1-2.9.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Stanislaus |
City | Modesto, Salida |
Zip Code | 95356, 95368 |
Senate District |
14 |
Assembly District | 25 |
Congressional District | 19 |
Caltrans District |
10 |
County/State Route | Stanislaus 219 |
Postmile Begin/End | 0.1 2.9 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 940 | 940 |
Lane Miles Added (HOV) | 0 | |
Lane Miles Added (Mixed) | 6.7 | 6.7 |
Peak Period Time Savings (minutes) | 37418 | 37418 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Caltrans | Zelie Nogueira | (209) 948-3930 | zelie.nogueira@dot.ca.gov | |
Design (PS&E) Phase |
Caltrans | Zelie Nogueira | (209) 948-3930 | zelie.nogueira@dot.ca.gov | |
Right of Way Phase |
Caltrans | Zelie Nogueira | (209) 948-3930 | zelie.nogueira@dot.ca.gov | |
Construction Phase |
Caltrans | Zelie Nogueira | (209) 948-3930 | zelie.nogueira@dot.ca.gov | |
Corridor System Management Plan |
Caltrans | Zelie Nogueira | (209) 948-3930 | zelie.nogueira@dot.ca.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
CMIA |
$14,760 | $-6,143 | $8,617 | ||||
Non-bond Funding | |||||||
State/Federal* |
$35,020 | $716 | $35,736 | ||||
Non Budgeted ETC |
$0 | $0 | $0 | ||||
Total**** | $49,780 | $-5,427 | $44,353 |
**** Totals may not add up exactly to column amounts due to rounding
# Approved is planned budget
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
||||
Environmental |
$1,520 | $128 | $1,648 | $1,621 | |||
Design(PS&E) |
$2,000 | $828 | $2,828 | $2,891 | |||
Right of Way |
$31,260 | $0 | $31,260 | $19,743 | |||
Construction |
$15,000 | $-6,383 | $8,617 | $8,564 | |||
Total* | $49,780 | $-5,427 | $44,353 | $32,820 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.
Project Schedule Baseline Summary | |||||||
---|---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
|
Begin Environmental Phase
End Environmental Phase |
10/01/1998 05/01/2004 |
|
10/01/1998 05/01/2004 |
100 | 10/01/1998 05/13/2004 |
0 0 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
10/01/2004 06/01/2007 |
|
10/01/2004 06/01/2007 |
100 | 05/13/2004 06/28/2007 |
4 -1 |
|
Begin Right of Way Phase
End Right of Way Phase |
01/01/2005 06/01/2007 |
|
01/01/2005 06/01/2007 |
100 | 10/01/2004 03/10/2008 |
3 -9 |
|
Begin Construction Phase
End Construction Phase |
11/01/2007 08/01/2009 |
|
11/01/2007 08/01/2009 |
100 | 07/09/2008 06/30/2010 |
-8 -11 |
|
Begin Closeout Phase
End Closeout Phase |
10/01/2009 11/01/2009 |
|
10/01/2009 11/01/2009 |
0 | 06/30/2010 07/28/2016 |
-9 -82 |
|
Corridor System Management Plan |
|||||||
Adoption Date | 10/01/2008 | 10/01/2008 | 0 | 09/28/2008 | 0 | ||
Implementation Date | 02/01/2009 | 02/01/2009 | 0 | 0 |
????????
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 940 | 940 |
Lane Miles Added (HOV) | 0 | |
Lane Miles Added (Mixed) | 6.7 | 6.7 |
Peak Period Time Savings (minutes) | 37418 | 37418 |
Bond Funding Cost | |
---|---|
Adopted: |
$14,760,000 |
Current Approved: |
$9,844,000 |
Actual Expenditures: |
$8,564,000 |
Status as of December 31, 2023.